Report to Casco Bay Families on Arena

Due to unexpected delays in the construction process, the Casco Bay Arena will not be operational for the 2014-15 season. To avoid incurring additional borrowing costs, we will complete all of the site and foundation work, and suspend construction operations until April 1, 2015. The completed Arena will be delivered no later than September 30, … More Report to Casco Bay Families on Arena

Step 6: Installation of Footings and Foundation Started

The construction of the Arena is moving full speed ahead, and the outlines of the building can be seen as the footings and foundation perimeter have been poured. Click below to see a time lapse of the pouring of the footings. We need your support more than ever. We presently have a gap of $150,000 … More Step 6: Installation of Footings and Foundation Started

Step 5: Financing Closed for Casco Bay Arena; $150,000 Must Be Raised to Complete Arena

On September 15th, the most important step in our construction process was reached–financing for the Arena was closed with Bangor Savings Bank, CEI, Inc. and Greater Portland Council of Governments.  To see a time lapse of Weeks 2 & # of the construction project, click below: With the closing of the construction loan, the foundation … More Step 5: Financing Closed for Casco Bay Arena; $150,000 Must Be Raised to Complete Arena

Final Pledges Needed to Complete Construction

The Casco Bay Arena was recently featured in a Portland Press Article by Mark Emmert, which can be found at: http://www.pressherald.com/2014/08/07/new-hockey-rink-opening-in-falmouth We are in the final stages of the financing process and need to show our lenders that there is support for the Arena.  We need to secure $150,000 in pledges for donations to make … More Final Pledges Needed to Complete Construction

Special Thanks to Steve Blais and Blais Civil Engineers

The hard work of Steve Blais, PE is one of the main reasons our Arena project is ready to go.  Steve has worked tirelessly on the various civil engineering issues that often go unnoticed.  Needless to say, these site and design issues are often the most important issues. Without Steve’s commitment to the project and … More Special Thanks to Steve Blais and Blais Civil Engineers

Step 4: Falmouth Approves Project

On May 28th, the Falmouth Town Council unanimously approved the project plan, rezoning and 40-year land lease for the Arena.  Council Chair Teresa Pierce was an early supporter of the Arena and deserves special thanks along with fellow councilors Chris Orestis, Sean Mahoney, Karen Farber, David Goldberg, Claudia King, and Russ Anderson.  Town Manager Nathan Poore, … More Step 4: Falmouth Approves Project

Casco Bay Arena Awarded $50,000 Solar Grant

Efficiency Maine recently awarded Casco Bay Arena a $50,000 grant for installation of a photovoltaic system.  This is an important first step in our goal of having Maine’s first net-zero electricity arena. EM-013-2014 Notice of Award 05 15 14 Casco Bay Coach Mike Curtis has taken the lead on our sustainability efforts.  Presently, we are … More Casco Bay Arena Awarded $50,000 Solar Grant