Step 9: Install the Boards and Get Ready for the Ice

The Arena is quickly coming together and we will be ready for our Opening Day on October 23rd.  The boards are in, the warm area is being finished, and we are ready to install ice this week.  For a time-lapse video of the recent construction, please click on the link below. The Forecaster and Bangor … More Step 9: Install the Boards and Get Ready for the Ice

Step 6: Installation of Footings and Foundation Started

The construction of the Arena is moving full speed ahead, and the outlines of the building can be seen as the footings and foundation perimeter have been poured. Click below to see a time lapse of the pouring of the footings. We need your support more than ever. We presently have a gap of $150,000 … More Step 6: Installation of Footings and Foundation Started

Step 5: Financing Closed for Casco Bay Arena; $150,000 Must Be Raised to Complete Arena

On September 15th, the most important step in our construction process was reached–financing for the Arena was closed with Bangor Savings Bank, CEI, Inc. and Greater Portland Council of Governments.  To see a time lapse of Weeks 2 & # of the construction project, click below: With the closing of the construction loan, the foundation … More Step 5: Financing Closed for Casco Bay Arena; $150,000 Must Be Raised to Complete Arena

Demo & Site Work Begins; Pledges Needed to Complete Construction

On August 18th, demolition and site work finally began.  Last week, Scott Dugas Trucking & Excavation leveled the site, and began excavation work so that the foundation and slab can be poured. For a time lapse of the first week’s worth of work, click below: To complete the Arena for the 2014-15 season, we desperately … More Demo & Site Work Begins; Pledges Needed to Complete Construction